Construction oversight of a building with the concrete checked in the laboratory, delivery by delivery.
What we did
- Concrete control with an external laboratory: orders, volume checks and strength results.
- Thirty-two progress statements reviewed.
- Twenty-four oversight reports.
- Review of structural changes during construction.
- Contracts, bid comparisons and close-outs.



The works, month by month
Mar – Apr 2024
Excavation, ground anchors and retaining wall.
May – Jun 2024
Footings, foundations and basement and semi-basement columns.
Jul – Sep 2024
Lobby, floor 2 and slabs up to floor 7, with their stairs.
Oct – Nov 2024
Slabs of floors 8 to 10, roof and masonry.
Dec 2024
Basement slab, water tank and elevator overrun.
2025 – 2026
Follow-up with monthly reports until January 2026.
Checks and tests
- Check of the steel in every slab before the pour.
- Concrete control with an outside laboratory.
- Review of the ground anchors.
- Review of structural changes.
What each service included
Construction oversight (interventoría). We represent the owner: quality, schedule and budget on public and private projects.
Structural design. Concrete, steel and masonry buildings designed to the NSR-10, from the first concept to the reinforcement details.