Structural design and construction oversight of the building.
What we did
- Structural design.
- Construction oversight.



The works, month by month
Nov 2023
Demolition of the existing building.
Mar 2024
Foundations and semi-basement structure.
May 2024
Semi-basement retaining wall, slabs 1 and 2 and columns.
Jun – Jul 2024
Slabs 3 to 6 and columns.
Aug 2024
Structure complete, recorded from the air.
Dec 2024
Finishes progress report and documents for the Certificado Técnico de Ocupación (CTO).
Checks and tests
- Slump tests and delivery tickets for every concrete pour.
- Concrete control.
- Rebar schedules.
- Progress valuations by front: excavation, structure, plumbing and lightweight walls.
- Site and management meetings.
What each service included
Structural design. Concrete, steel and masonry buildings designed to the NSR-10, from the first concept to the reinforcement details.
Construction oversight (interventoría). We represent the owner: quality, schedule and budget on public and private projects.